some IE formula use in garments production

(1/1)

MEGH:


    Capacity
Capacity = 60 / Capacity time in minute

    Cycle Time
Cycle Time = 60 / Team target

    Team target
Team target = (Work hour/SMV) * Present operator * Organizational efficiency

    Capacity Achievable
Capacity Achievable = Capacity * Balance

    Balance
Balance = BPT / Bottle neck time (BNT)

    Standard time
Standard time = Net operation time * (1 + Ratio of loss time)

    Daily output
Daily output = Work hour / SMV



    Factory capacity
Factory capacity = (Work hour / SMV) * Total worker * Working day * Efficiency


    CPM
CPM = (Total over head cost of the month / No of SMV earners * Work minutes) *Efficiency 



    Required no of operator
Required no of operator = Target daily output / Daily output per operator


    CM of garments
CM of garments = Total production / (No of worker * Work hour)


    Marker Efficiency
Marker Efficiency = (Total area of marker / Total area of lay) * 100


    CPD (Consumption per dozen)
CPD = Marker length * Marker width * GSM * 12 / (1000 * 100 * 100 * Total marker pc’s)