Capacity
Capacity = 60 / Capacity time in minute
Cycle Time
Cycle Time = 60 / Team target
Team target
Team target = (Work hour/SMV) * Present operator * Organizational efficiency
Capacity Achievable
Capacity Achievable = Capacity * Balance
Balance
Balance = BPT / Bottle neck time (BNT)
Standard time
Standard time = Net operation time * (1 + Ratio of loss time)
Daily output
Daily output = Work hour / SMV
Factory capacity
Factory capacity = (Work hour / SMV) * Total worker * Working day * Efficiency
CPM
CPM = (Total over head cost of the month / No of SMV earners * Work minutes) *Efficiency
Required no of operator
Required no of operator = Target daily output / Daily output per operator
CM of garments
CM of garments = Total production / (No of worker * Work hour)
Marker Efficiency
Marker Efficiency = (Total area of marker / Total area of lay) * 100
CPD (Consumption per dozen)
CPD = Marker length * Marker width * GSM * 12 / (1000 * 100 * 100 * Total marker pc’s)